| In July 2005, MainPower commenced a project to re-insulate the existing 33kV line between Waipara and Kaikoura to 66kV. This key capital project has been broken down into two major stages, with Stage 1 covering from Waipara to Cheviot and stage 2 covering from Cheviot to Kaikoura. This project will be completed with over 475 steel extensions being erected and 130 poles changed to allow the new 66kV insulators to be installed. | ![]() |
| Stage 1 of the 66kVA line project and installation of sub stations was completed early November 2007. The livening of the three new skid substations located at Mackenzie Road, Greta Valley and Cheviot were undertaken over a 6 day commissioning period, requiring the utilisation of the 1,250kVa generator to 80 extensions (budget 316), 40 strain poles (budget 178) and 90 in line poles (budget 331) ensure the surrounding districts were not affected by the shutdown of the sub stations. | ![]() |
| Stage 2 of the project began during 2007 with the 66kV line construction project (Cheviot to Kaikoura) 25% complete at the end of 2007, with 209 of the 836 structures changed. The line construction should be completed in 2008. MainPower has established a dedicated project team and purchased specialised equipment to undertake the project. The upgraded line will ensure MainPower has a security of supply to Kaikoura without relying on the existing line via Transpower's circuit. | ![]() |
MainPower are currently upgrading the power supply to the northern part of the Kaiapoi township, to meet growing demand in the area. Stage 1 of the project has been completed, involving the laying of over 1km of dual-circuit cables from the Island Rd substation to Adderley Terrace. It is expected that the cable-laying work will be completed by September, after which the cables will be livened to spread load in the northern part of Kaiapoi and increase the capacity and security of supply to customers in the area. This is a significant project for MainPower, and involves some difficult work installing cables underneath riverbeds and rail crossings. We appreciate that this work has had some impact on local residents as trenching has taken place, and we would like to thank residents of Audley Street, Sneyd Street and Adderley Terrace for their co-operation to date. | ![]() |
| MainPower has been engaged by Infinity Group to provide power reticulation to the new Pegasus Township. The project will span approximately 3-4 years and will see the power reticulation being installed for the new township. The project commenced in June 2007 with a dedicated project team being established to provide the installation of the underground cabling and installation of the streetlight network. MainPower has developed a solid working relationship with Heb March, the projects civil contractor, which has seen the completion of the Mapleham entrance way and Stage 1 of the township completed in November 2007 although delayed somewhat on the original project time frames. | ![]() |
MainPower are currently upgrading the power supply to the northern part of the Kaiapoi township, to meet growing demand in the area. Stage 1 of the project has been completed, involving the laying of over 1km of dual-circuit cables from the Island Rd substation to Adderley Terrace. It is expected that the cable-laying work will be completed by September, after which the cables will be livened to spread load in the northern part of Kaiapoi and increase the capacity and security of supply to customers in the area. This is a significant project for MainPower, and involves some difficult work installing cables underneath riverbeds and rail crossings. We appreciate that this work has had some impact on local residents as trenching has taken place, and we would like to thank residents of Audley Street, Sneyd Street and Adderley Terrace for their co-operation to date. | ![]() |
Location http://www.mainpower.co.nz/index.cfm/1,403,0,42,html
Copyright © Mainpower 2013
MainPower New Zealand Limited and Utility Online 5 High Street Ph 03 311 8300 Email info@mainpower.co.nz Faults within the MainPower area: Ph 0508 60 70 80 |